Choosing a reactor technology, systematically
How to use the IAEA Reactor Technology Assessment (RTA) method to compare nuclear power plant designs against your own objectives — and arrive at a choice you can explain and defend.
Based on IAEA Nuclear Energy Series No. NR-T-1.10 (Rev. 1), Nuclear Reactor Technology Assessment for Near Term Deployment (2022), with process guidance from EPRI report 3002025344, Owner-Operator Reactor Technology Assessment Guide — 2022 Version. Section references such as IAEA §4.1 point to those documents.
Contents
What the RTA method is
RTA is a decision-making method. It does not tell you which reactor is "best" in general; it tells you which of the available designs best meets your stated objectives, and it leaves a written trail showing why. IAEA §1.2, §2.2
Ten key elements (KEs) broken into 73 key topics (KTs) — from site fit and fuel cycle to safety, readiness, delivery and cost. IAEA §5
Each design is scored on each topic on one fixed scale, then weighted and added up — the simple multi-attribute rating technique (SMART). IAEA §4.1
A preferred design with at least one alternative, ranked and justified, ready to feed the feasibility study and bid specification. EPRI §2.1.6
- KE weights add up to 100%. Within each KE, the KT weights add up to 100%.
- Scores run from 1 (least meets the rationale) to 5 (best fit), so the total also lands on a 1–5 scale.
- Weights come from your policy objectives; scores come from evidence about each design. Keep the two separate.
An "ideal" reactor is the one that best fits your weighted objectives, carries risks you are willing to accept, and still comes out on top when reasonable people change the weights. Everything in this guide serves those three tests.
The process in seven steps
This sequence combines the IAEA pre-RTA steps and matrix with EPRI's screening funnel. Do the steps in order. EPRI warns that objectives not fully worked out at the start can taint the results of the whole assessment, and the IAEA requires the rationale for each weight to be written before the weights are assigned. EPRI §2.2 IAEA §5
-
Fix the objectives
Write down, and have decision makers approve, what the programme or project must achieve — usually four to eight objectives — and rank them. IAEA §3.1–3.2 EPRI §2.2
-
Turn objectives into criteria
Map each objective to the KEs and KTs that measure it. Mark which criteria are hard requirements (knock-outs) and which are preferences to be scored. IAEA §3.1 EPRI §2.1, §2.5
-
Build the long list and screen it
Survey available technologies, remove those that clearly cannot meet the requirements (with a written reason), and narrow to three to five comparable candidate designs. IAEA §3.3, §4.2 EPRI Steps 2–5
-
Set the weights
Write a rationale for each KE's importance, then assign KE weights (sum 100%) and KT weights within each KE (sum 100%). Do this before looking at vendor data. IAEA Annex, Fig. A-1
-
Define the scoring scales
For every KT, write what earns a 1, 2, 3, 4 and 5, using one scale throughout and a realistic range of values. IAEA §4.1, Table 6 EPRI §2.4
-
Collect evidence and score
Send every vendor the same questions, score each design against the rubric, and record the justification for every score. IAEA §4.3, Annex
-
Aggregate, test, decide, document
Compute totals, test sensitivity to the weights, compare the issues numbers cannot capture, check the result against the original objectives, and write it up. IAEA §2.2.3, Table 5 EPRI §2.1.6, §2.3
The funnel
Effort increases as the field narrows: cheap, public-information screening first; detailed vendor engagement only for the few designs that survive. EPRI §2.1
- Technologies of interestPWR, BWR, PHWR, HTGR, SFR, LFR, MSR, SMR types … — broad, from public data
- Candidate technologiesKnock-out and avoidance screening
- Potential designsVendor-specific designs of those technologies
- Candidate designs · 3 to 5Second screening; engage vendors, NDAs
- RTA matrixWeighted scoring on KEs / KTs
- Proposed design + alternativesRanked, stress-tested, documented
When RTA is used
RTA is not a one-off study. It runs alongside the IAEA Milestones approach and is repeated with more detail at each phase; issues found at one phase are carried into the next. IAEA §1.1, §2.1
Screen the market
Typically run by the NEPIO. A limited-scope RTA — often a market survey using public sources such as the IAEA ARIS database — to categorize technologies that could meet the policy objectives, together with their fuel cycles.
Assess in detail
Typically run by the owner/operator organization. Full RTA with vendor information obtained under non-disclosure agreements and a uniform question set; selects the reactor types and technology holders to invite. Ends at the milestone "ready to invite/negotiate bids".
Compare the bids
The RTA evaluates the competing bids against each other once all bid information is in, in line with IAEA NG-T-3.9 on invitation and evaluation of bids.
Which key elements are included in each phase
| Key element | Phase 1 | Phase 2 | Phase 3 |
|---|---|---|---|
| KE1 Site and environment | No | Yes | Yes |
| KE2 Fuel cycle | Yes | Yes | Yes |
| KE3 Nuclear safety | Yes | Yes | Yes |
| KE4 Nuclear island design and performance | Yes | Yes | Yes |
| KE5 Balance of plant (BOP) design and grid integration | Yes | Yes | Yes |
| KE6 BOP design for purposes other than electricity production | Only when a non-electric application is planned | ||
| KE7 Safeguards and protection | No | Yes | No |
| KE8 Technology readiness | Yes / No | Yes | No |
| KE9 Project delivery | No | Yes | Yes |
| KE10 Economics and financing | No | Yes | Yes |
From IAEA Table 7. Phase 1 usually omits KE1 (no site chosen yet) and KE7 (safeguards assumed to be met). By Phase 3, readiness and safeguardability have been settled with the vendors or the design eliminated. Economics is often hard to quantify early or handled by a separate team. KE2–KE5 can always differentiate technologies and belong in every phase.
Countries or utilities that already operate nuclear plants use the same method; their policy objectives usually exist already, and they rely less on external consultants. IAEA §2.1, §2.2.2
Before you score
The IAEA calls these the pre-RTA steps. They decide the quality of everything that follows. IAEA §3
4.1 Write the policy objectives
Start from the national energy policy (or, for a utility, the business case) and answer three questions in writing:
- Under what conditions does this programme or project make sense?
- Why was this course of action chosen?
- Which specific outcomes will count as success?
Then select the objectives that matter most — typically four to eight — rank them, and have the policy maker assign relative weights that sum to 100%. Typical candidates include: maintain nuclear safety performance; produce electricity at competitive cost; meet the energy plan's capacity and timing; build national participation and technology transfer; use proven technology; secure long-term vendor support, components and fuel; develop local industry and people; minimise environmental impact; and keep schedule and financing cost under control. IAEA §3.1–3.2, Tables 3–4
For an owner-operator, EPRI frames the same step as mission and business objectives: end-product (electricity, heat, hydrogen …) and its business case, required output, target location, service requirements (firm or flexible, black start, resilience), operating life, need dates, target budgets, and long-term goals such as fleet build-out. EPRI §2.2
4.2 Derive the criteria
Translate each objective into technology features that can be measured, using established requirement sets as a menu rather than a checklist: the IAEA Common User Considerations (NP-T-2.1), the European Utility Requirements, and EPRI's Utility Requirements Documents for advanced LWRs and SMRs. Do not forget non-technical factors — vendor construction record, technology transfer history, political considerations, national resources — which can dominate a decision. IAEA §3.1, Tables 1–2
4.3 Classify every criterion
EPRI's three-tier classification is the cleanest way to keep hard requirements out of the scoring. Word them precisely: do not write a preference as a requirement, or the reverse. EPRI §2.1, §2.5
| Type | Typical wording | How it is used | Example |
|---|---|---|---|
| Exclusionary | must, minimum, maximum, requirement | Go / no-go. A design that fails is removed. | Output of at least 500 MWe. |
| Avoidance | strong preference, aim, want | Used as a screen, but relaxed if too few designs survive. | Prefer five or more years between refuellings. |
| Suitability | better / worse | Weighted and scored 1–5 in the matrix. | Between two acceptable outputs, the one that better fits demand scores higher. |
4.4 Build and screen the long list
- Sources. The IAEA Advanced Reactors Information System (ARIS), licensing submissions and environmental assessments published by regulators, third-party studies, and vendor information. In Phase 2, detailed data normally requires an NDA and a uniform questionnaire sent to every vendor. IAEA §4.3
- Eliminate first, with reasons. Remove unsuitable technologies with a written justification tied to the objectives before any scoring. IAEA §4.2
- Compare like with like. One large unit and several co-located SMRs can deliver the same ~1200 MWe but behave very differently on many KTs. Run separate RTAs for large WCRs and for SMRs, and decide "large or small" at a higher level. IAEA §4.2
- Aim for three to five candidates. If only one design survives, do not treat it as the answer: relax avoidance factors or carry the best rejected design forward as a comparator. EPRI §2.1.5
- Compare the same scope. Some vendors offer only the nuclear island. Make sure every design is assessed over the same plant boundary. EPRI §2.2
4.5 Set up the team and the paperwork
- The NEPIO (Phase 1) and the owner organization (Phase 2) take full responsibility for the RTA; the team reports to the top decision makers. IAEA §2.2.2
- Collectively the team needs full expertise in design, engineering, construction and operation, plus working knowledge of fuel, fuel cycles and waste. EPRI adds roles for transmission planning, communications and commercial contracting, alongside an executive manager, project manager, technical specialists and existing plant operating staff. IAEA §2.2.2 EPRI App. B
- Consultants and universities fill gaps, but their reports are inputs to the team, not the sole basis for a decision. IAEA §2.2.2
- Quality rests on three things: well-defined national requirements, enough objective information on each design, and a team qualified across all KEs. Set document control and review/approval rules at the start. IAEA §2.2.3
- Plan for the effort: EPRI estimates a full owner-operator assessment takes six months to two years. EPRI Exec. Summary
Running the RTA matrix
The RTA matrix is a table with one row per key topic, a weight for each, and a score column per design. The IAEA Annex sets out the order of work below; the workbench implements it. IAEA Annex, Fig. A-1
-
Weight the key elements
Write a short rationale for each KE's importance to your objectives, then assign percentages summing to 100%. IAEA Table 7 gives High / Medium / Low starting points for large WCRs, SMRs and non-electric use (shown in section 7). A "Low" rating reflects how little a KE is expected to separate the designs in that setting — not that the subject is unimportant.
-
Weight the key topics inside each element
Write a rationale per KT and assign weights that sum to 100% within the KE. Split a KT into sub-topics if needed (the Annex divides KT 1.2 into wind and seasonal variation, 50% each). Give a KT zero weight when it does not apply — KT 8.1 (SMR readiness) for large WCRs, for example. Weights may also reflect how much information is realistically available.
-
Write the scoring rubric
For each KT, define what earns each score from 1 to 5, anchored to your site and requirements (the Annex, for a site needing a 0.2 g design basis, uses "5: seismic design 0.3 g … 1: cannot withstand 0.12 g or no information"). Two rules keep the matrix unbiased:
- One scale everywhere. Never give important topics a wider range (1–10) and minor ones a narrower range (1–5); importance belongs in the weights. IAEA §4.1
- A realistic range. Anchor scores to the range real designs occupy — see the capacity-factor example in section 6. When the data cannot separate two designs with confidence, score them equally. IAEA §4.1, Table 6
-
Collect evidence and score
Send every vendor the same questions (the key element reference lists examples). Score each design against the rubric and write one line of justification per score. Mark scores that await vendor answers as provisional (in the workbench, use the notes field). A score of 1 for "no information" is given only after the vendor has been asked and has not answered adequately. IAEA Annex, note to Table A-1
-
Aggregate
Multiply each score by its KT weight and sum within the KE; multiply each KE result by the KE weight and sum across KEs. The result is a total on the 1–5 scale for each design. IAEA §4.1 EPRI §2.3
-
Stress-test
Re-run the totals with different weight sets — for example the weights preferred by different stakeholder groups — and check whether the leader changes. Then compare the qualitative issues the numbers cannot capture, and check each finalist against every original objective (exceeds / meets / partially meets / does not meet). EPRI §2.1.6, §2.3, Table 2-4
-
Decide and document
Name a proposed design and at least one alternative. Record the weights and their rationale, the rubrics, the evidence behind each score, the sensitivity results and the open questions. This record carries into the feasibility study, bid specification and bid evaluation. IAEA §2.2.3 EPRI §2.1.6
It is tempting to raise the weight of a criterion because one design looks risky on it. EPRI calls this improper: weights express how important a criterion is to your objectives. Risk in a particular design belongs in that design's score — a riskier design scores lower on the same criterion. EPRI §2.6
One key element, scored end to end
The IAEA Annex scores three large WCR designs for the fictitious country "Retasland" on KE1, Site and environment. The weights and scores below are from Table A-1; the weighted sums are calculated here.
| KT | Topic | Weight | NPP1 | NPP2 | NPP3 |
|---|---|---|---|---|---|
| 1.1 | Site seismicity | 25% | 5 | 2* | 4 |
| 1.2 | Meteorology and hydrology | 25% | 5 | 1* | 2* |
| 1.3 | Water resources | 5% | 4 | 3* | 5 |
| 1.4 | Population | 5% | 5 | 4 | 2 |
| 1.5 | Site access | 5% | 5 | 4 | 3 |
| 1.6 | Site size | 15% | 1 | 4 | 5 |
| 1.7 | Environmental and radiological impact | 5% | 5 | 4 | 2* |
| 1.8 | Other external events | 15% | 4 | 3 | 1 |
| KE1 score = Σ (weight × score) | 100% | 4.20 | 2.55 | 3.00 | |
* The Annex marks these scores "more info" — provisional until the vendor answers. KT 1.2 combines two sub-topics weighted 50/50 that received identical scores.
How to read it:
- Arithmetic. NPP1 = 0.25×5 + 0.25×5 + 0.05×4 + 0.05×5 + 0.05×5 + 0.15×1 + 0.05×5 + 0.15×4 = 4.20.
- Provisional scores matter. NPP2 trails mainly on the two heaviest topics — and both of those scores are waiting on vendor information. Its KE1 result could move a long way once the questions are answered.
- Watch for hidden knock-outs. NPP1 leads despite scoring 1 on site size (15% weight). If its footprint truly cannot fit the site, that is an exclusionary issue, not something a weighted average should absorb.
- Roll-up. KE1 is one element. If KE1 carried, say, 15% of the total, these results would contribute 0.63, 0.38 and 0.45 points to the three totals.
- Justify every score. The Annex records reasons such as a heaviest component of 330 t × 3.85 m high (NPP1, scored 5) versus 700 t × 5 m (NPP3, scored 3) for transport over the site's roads and bridges.
Setting an honest scale: capacity factor
Three designs have capacity factors of 75%, 88% and 94%. Scored on a 0–100% scale in 25-point steps, all three crowd into the top two scores and the scale barely separates them. Scored on a relevant range (below 80% = 1, 80–84% = 2, 85–89% = 3, 90–95% = 4, above 95% = 5) they score 1, 3 and 4 — the difference that matters becomes visible. IAEA §4.1, Table 6
The 10 key elements
What each element covers, when it separates designs, typical importance, its key topics and example questions for vendors. Topic descriptions are condensed from IAEA §5; open an element to see the detail.
Importance ratings are IAEA's examples, compiled from Member State feedback and expert opinion. The IAEA is explicit that the policy team sets the actual ranges, values and rationale.
Fitting the weights to your situation
Your circumstances, not the reactor catalogue, decide which elements carry weight. These are the most common shifts, each grounded in the source documents.
| If your situation is… | Give more weight to | Why |
|---|---|---|
| Small or weakly interconnected grid | KT 5.6, KT 5.2, KT 4.1 | A single unit is commonly kept below about 10% of grid capacity to avoid instability; this is a key reason SMRs suit small grids. IAEA KT 5.2 |
| First nuclear plant in the country | KT 8.2, KT 9.1, KT 9.4, KT 8.3 | Newcomers are expected to follow a reference plant already licensed in the vendor's country; the owner's scope, technology transfer and long-term support are critical. IAEA KT 8.2, KT 9.4 |
| Firm, near-term need date | KE8, KT 4.2, KT 9.3 | If a design will not be ready in time, how good it will eventually be does not matter; restrict to mature designs or screen out low readiness. EPRI §3.3 |
| Heat, hydrogen or desalination as a product | KE6 (all KTs) | KE6 becomes High; coupling hazards and delivered steam conditions dominate, and direct heat use is markedly more efficient than electricity. IAEA §5.6, Table 7 |
| Fuel supply security is a policy goal | KT 2.1, 2.2, 2.3, 2.7, 9.6 | HALEU and novel fuels have fewer suppliers than conventional LEU; the number of qualified fabricators matters. IAEA KT 2.1–2.3 |
| Limited capital or financing capacity | KT 10.1, KT 10.6, KE9 | Smaller up-front investment and phased units can ease financing, but first-of-a-kind cost and schedule are less certain. IAEA KT 10.1, 10.6 |
| Site already chosen; seismic, water or land constrained | KE1 (KT 1.1, 1.3, 1.6) | Site–design interaction is a strong differentiator for large-capacity sites. IAEA §5.1 |
| High share of variable renewables | KT 4.8, KT 5.5, KT 6.8 | Load following, ramp rates and integration with hybrid systems become decisive. IAEA KT 4.8 |
| Plans for a fleet of units | KT 4.4, KT 5.4, KT 9.2 | Standardization and supply-chain strength pay off over many units. IAEA KT 4.4 EPRI §2.2 |
If a condition is non-negotiable — the grid cannot take more than a given unit size, or the plant must be operating by a fixed year — make it an exclusionary criterion in screening rather than a heavy weight in the matrix.
Reading the result
The ranked totals are a guide, not the decision. EPRI is explicit that the proposed design should reflect everything known about the candidates, not the numerical score alone. EPRI §2.1.6 Before naming a winner, run these five checks.
Completeness
Every design is scored on every weighted topic, with evidence. Treat any total that rests on missing or provisional scores as provisional.
Knock-outs
Look for low scores (1–2) on heavily weighted topics. A good average can hide a disqualifying weakness; if it is disqualifying, handle it as an exclusion. EPRI §2.4
Margin versus uncertainty
If the gap between the top two is small compared with how uncertain the scores are, treat it as a tie and let the qualitative comparison decide. Claims for designs without operating history carry more uncertainty than records from operating fleets. IAEA KT 3.7, KT 4.2
Sensitivity
Change each KE weight up and down, and try the weight sets of different stakeholders. A leader that survives is a robust choice; one that flips needs a sharper argument. EPRI §2.3
Issues and alignment
Tabulate issues that do not reduce to a number (fuel qualification, site fit, remaining design work, grid flexibility) side by side, then rate each finalist against every original objective. EPRI Tables 2-3, 2-4
Overnight capital cost and levelized cost comparisons are only meaningful between designs with similar maturity and risk. EPRI notes they are "easy to calculate but difficult to get right"; for less mature designs, account for schedule and development risk explicitly. EPRI §3.5
Common pitfalls
| Pitfall | Do instead |
|---|---|
| Starting without approved, written, ranked objectives. | Fix and approve objectives first; everything else refers back to them. IAEA §3.1 EPRI §2.6 |
| Setting or adjusting weights after seeing vendor scores. | Write rationales and weights before scoring; record any later change and why. IAEA §5 |
| Different scoring ranges for "important" and "minor" topics. | One scale for every topic; importance lives in the weights. IAEA §4.1 |
| Scales so wide that real designs all score the same. | Anchor scales to the realistic range of industry data. IAEA Table 6 |
| Mixing large WCRs and SMRs in one matrix. | Run separate RTAs; choose large versus small at a higher level. IAEA §4.2 |
| Scoring missing information as 1 straight away. | Ask the vendor first; score 1 only after no or inadequate response. IAEA Annex |
| Adding risk to the weights. | Reflect risk in the affected design's scores. EPRI §2.6 |
| Taking only one design into the detailed evaluation. | Keep a comparator; a single survivor removes options and invites bias. EPRI §2.1.5 |
| Letting a consultant's report stand in for the team's judgement. | Consultant input feeds the team's analysis. IAEA §2.2.2 |
| Counting the same benefit twice (e.g. simplification and lower capital cost). | Assign each benefit to one KT. IAEA KT 4.5, 4.6 |
| Treating the top total as the decision. | Run sensitivity, issue comparison and alignment checks, then decide. EPRI §2.1.6 |
IAEA and EPRI side by side
The two documents share one logic — objectives, screening, weighted scoring, judgement — at different levels. Use the IAEA structure for the matrix; borrow EPRI's screening vocabulary and decision checks.
| IAEA RTA (NR-T-1.10 Rev. 1) | EPRI Owner-Operator RTA Guide (2022) | |
|---|---|---|
| Written for | Member States — the NEPIO and owner/operator in a national programme | A single owner-operator making a business decision |
| Structure | 10 key elements, 73 key topics, optional sub-topics | 5 criteria groups, 31 criteria |
| Flow | Pre-RTA steps, then the matrix; repeated in Milestones Phases 1–3 with rising detail | 6 steps: objectives → technologies → screen → designs → screen → proposed and alternatives |
| Screening | Remove unsuitable technologies with justification before assessment | Exclusionary and avoidance factors at Steps 3 and 5 |
| Scoring | SMART; 1–5 (or 1–9) scale; weights sum to 100% | Utility functions on 1–5; weight × rating summed to a composite suitability value |
| After scoring | Validate the selection against the problem definition (listed as the final decision step, not detailed further) | Issue comparison, alignment with business objectives, sensitivity studies |
Where EPRI's criteria sit in the IAEA matrix
| EPRI criteria group | Main IAEA home |
|---|---|
| Basic operations — energy output, general O&M, fuel selection, used fuel, good neighbour | KT 4.1–4.2, KT 4.7, KE2, KT 1.7 |
| Site selection and characterization | KE1 |
| Maturity and remaining effort — design maturity, licensing, OEM, supply chain, owner capability | KE8, KT 9.1–9.2, KT 2.2 |
| Technology capabilities — design philosophy, safety, SSCs, I&C and cyber, O&M, flexibility, fuel cycle, proliferation resistance, licensing, constructability | KE3, KE4, KE5, KE7, KE2 |
| Cost and commercial — overnight cost, LCOE, other costs, commercial terms | KE10, KT 9.5 |
Your RTA checklist
Tick items as you go; progress is saved in this browser only.
0 done ·
Prepare
Screen
Score
Decide
Glossary
- RTA
- Reactor technology assessment — the IAEA decision-making methodology for selecting the most suitable reactor technology.
- KE / KT / ST
- Key element / key topic / sub-topic — the three levels of the RTA criteria hierarchy.
- SMART
- Simple multi-attribute rating technique — weight the criteria, score the options, add up. Alternatives include AHP, TOPSIS and ELECTRE.
- NEPIO
- Nuclear energy programme implementing organization — leads Phase 1 in a newcomer country.
- PFS / FS
- Pre-feasibility study (Phase 1) / feasibility study (Phase 2).
- BIS
- Bid invitation specification.
- WCR
- Water-cooled reactor; "large WCR" means large, grid-scale water-cooled units (PWR, BWR, PHWR), as distinct from SMRs.
- SMR
- Small modular reactor; definitions vary, commonly up to about 300 MWe per unit. Microreactors are commonly defined as up to about 50 MWe.
- FOAK / NOAK
- First-of-a-kind / Nth-of-a-kind plant.
- NSSS / BOP
- Nuclear steam supply system / balance of plant (turbine island and support systems).
- DiD
- Defence in depth — five levels of protection defined in IAEA SSR-2/1 (Rev. 1), kept as independent of each other as practicable.
- DSA / PSA
- Deterministic safety analysis / probabilistic safety assessment.
- CDF / LERF
- Core damage frequency / large early release frequency — typical PSA safety goals.
- SAR / OLCs
- Safety analysis report / operational limits and conditions (technical specifications).
- O&EPs / SAMGs
- Operating and emergency procedures / severe accident management guidelines.
- HALEU
- High-assay low-enriched uranium, enriched between 5% and 20% U-235.
- MOX
- Mixed uranium–plutonium oxide fuel.
- EPZ
- Emergency planning zone.
- UHS
- Ultimate heat sink.
- TRL
- Technology readiness level, a maturity scale used by EPRI and others.
- OCC / LCOE
- Overnight capital cost (excluding financing) / levelized cost of electricity (or energy).
- PPE / SPE
- Plant parameter envelope (bounding values across several designs) / site parameter envelope (one design's site requirements).
- ARIS / PRIS
- IAEA Advanced Reactors Information System / Power Reactor Information System.
- CUC / EUR / URD
- IAEA Common User Considerations / European Utility Requirements / EPRI Utility Requirements Document.
Sources and further reading
Primary sources
- International Atomic Energy Agency (2022). Nuclear Reactor Technology Assessment for Near Term Deployment. IAEA Nuclear Energy Series No. NR-T-1.10 (Rev. 1). Vienna: IAEA.
- Electric Power Research Institute (2022). Advanced Nuclear Technology: Owner-Operator Reactor Technology Assessment Guide — 2022 Version. Report 3002025344. Palo Alto, CA: EPRI.
Referenced by those sources
- IAEA (2015). Milestones in the Development of a National Infrastructure for Nuclear Power. NG-G-3.1 (Rev. 1).
- IAEA (2011). Invitation and Evaluation of Bids for Nuclear Power Plants. NG-T-3.9.
- IAEA (2009). Common User Considerations (CUC) by Developing Countries for Future Nuclear Energy Systems. NP-T-2.1.
- IAEA Advanced Reactors Information System (ARIS): aris.iaea.org · Power Reactor Information System (PRIS): pris.iaea.org
- EPRI (2022). Site Selection and Evaluation Criteria for New Nuclear Energy Generation Facilities (Siting Guide) — 2022 Revision. 3002023910.
This is an independent explanatory guide. It is not an IAEA or EPRI publication and is not endorsed by either organization. Content is summarized and paraphrased; consult the original documents for authoritative wording, and national regulations for requirements. Weight starting points and examples are illustrative.